Source: Key West Citizen | Published: February 9, 2024
The Florida Keys Aqueduct continues to make progress on upgrading the main water transmission line, and while traffic impacts are expected to lessen after March, the project is expected to continue through February 2025.
FKAA contracted crews are now working in 1,000-foot sections throughout the entire project zone from Mile Marker 80 to Mile Marker 84 to install service pipe for the master meters and air relief valves, according to FKAA representatives.
The work may last for two to four days in each section and barricades may remain in place for seven to 10 days before and after work is completed in each section, according to the FKAA.
Connections across U.S. 1 will be installed in four locations. When that schedule is finalized, FKAA will share it on their website, Facebook, and X (Twitter) pages.
Work to install the remaining 1,600 feet of the transmission main, just south of Tea Table Crossing, is expected to begin in March 2024, according to the FKAA.
Pipe across Whale Harbor Crossing, via a directional drill is expected to be installed in March 2024.
The maintenance of the main water line will be an ongoing on project for years and decades to come.
“If you see us out there it means our system is getting better,” FKAA Executive Director Greg Veliz said. “By the time we get to that 130th mile of work, it’s going to be revisit this.”
The FKAA is reminding motorists that left-hand turns in the work zone are not permitted by the Florida Department of Transportation. Instead, drivers should continue past their destination, make a u-turn when legal to do so, and make a right-hand turn into their destination, according to the FKAA. The speed limit is 35 mph through the work zone.
If anyone has questions about the Islamorada Transmission Main Replacement Project, call 833-588-5865 or email community@fkaa.com. After-hours support is available at 305-296-2454.
For information about the project, visit https://bit.ly/islamoradaproject.