FKAA Water Line Work is Ahead of Schedule

Source: Keys Citizen | August 3, 2023 | Reporter: Timothy O'Hara

A much-needed Upper Keys project to upgrade the Florida Keys’ main water line, in one of its most problematic areas, is halfway done and two months ahead of schedule.

Construction crews for the Florida Keys Aqueduct Authority have reached the halfway mark on the Islamorada Transmission Main Replacement Project approximately two months ahead of schedule, according to FKAA Executive Director Greg Veliz. With 11,000 linear feet of the new 36-inch transmission main now installed along U.S. 1 between Mile Markers 80 and 82, crews are continuing to work northbound toward Mile Marker 84.

“I want to thank the top-notch crew we have working 24/7 Monday through Friday on this legacy project that will ensure access to clean drinking water for many years to come,” Veliz said. “Their continuous commitment to support the business community, residents and visitors is such an integral part of the success of this project.”

While traffic has continued to flow steadily along U.S. 1, a rolling lane closure of 1,000 to 1,500 feet has been in effect at the work zone, which is currently near Mile Marker 82. To support the businesses and those traveling, the rolling lane closure is being suspended for major holidays and events, such as the Fourth of July holiday and the recent lobster mini-season.

In April 2023, crews began installing the new transmission main via open-cut trench installation along U.S. 1. Additionally, 900 feet of new transmission main has also been installed underwater at Tea Table Relief bridge crossing via horizontal directional drill, to protect it from high winds and storm surges. An additional main will also be installed at the Whale Harbor bridge crossing, according to the FKAA.